[edit] Aim and benefits
Along with seasonal commissioning, aftercare support to the building end users is essential to improve building operational performance and to reduce the performance gap.
The BREEAM criteria overlaps government and BSRIA‘s soft landing requirements and helps ensure a smooth transition from handover through to full operation.
Face to face training for the facilities management (FM) team and the end users, also helps to optimise the use of building user guides, operation and maintenance manuals (O&Ms) and all other documents passed on at hand over stage.
Frequent meetings, and facilities to monitor utilities consumption enables enhanced seasonal commissioning and the identification of defects sooner rather than later.
[edit] When to consider
[edit] Design stage
If targeted, bring to the awareness of the client/design team that commitment is required and it needs to be included in the Employer’s Requirements (ERs) prior to tender so the potential contractors are aware that they need to allow for the service.
[edit] Post construction stage
Principal Contractors to appoint a team/individual in charge of aftercare duties, which then provide the meetings and training schedule and the list of potential attendees.
[edit] Step-by-step guidance
The Principal Contractor should demonstrate how they will:
- Present key information about the building, including the design intent and how to use the building to ensure it operates as efficiently and effectively as possible.
- Conduct on-site facilities management training, to include a walkabout of the building and introduction to and familiarisation with the building systems, their controls and how to operate them in accordance with the design intent and operational demands.
- Provide initial aftercare support for at least the first month of building occupation, e.g. on-site attendance on a weekly basis to support building users and management (this could be more or less frequent depending on the complexity of the building and building operations).
- Provide longer-term extended aftercare support for occupants for at least the first 12 months from occupation, e.g. a helpline, nominated individual or other appropriate system to support building users/management.
[edit] Questions to ask while seeking compliance
- Are the facilities specified for sub-metering and monitoring? Is there a Building Management System (BMS) specified and are all the sub-meters linked to the BMS?
- Who is in charge of appointing the aftercare team? Is it a contractor’s requirement or an independent party?
- Do you know the end users? So that the aftercare team can arrange a training schedule.
- If the end user is unknown or multi-tenanted, does the building have a central facilities manager to receive all the necessary training.
- Does the aftercare team have weekly and monthly meeting schedules for the first 12 months after occupation.
- Ask the client what sort of operational infrastructure and resources they have/intend to have in place to coordinate the collection and monitoring of energy and water consumption data once the building is occupied.
[edit] Tools and resources
[edit] Tips and best practice
- Remind contractors that they are actively involved with the building’s management team and ensure all the necessary meetings and schedules are drafted prior to handover.
- Ask for drafts of the contractor’s schedules etc prior to completion to check that they will meet BREEAM requirements.
[edit] Typical evidence
Construction programme demonstrating a handover meeting.
Contractor’s summary to demonstrate how they intent to present key information about the building, on-site facilities management training, timetable for a walkabout of the building and introduction to the building systems, their controls and how to operate them.
Extract from the contractor commitment to provide initial aftercare support for at least the first month of building occupation.
Extract from the contractor commitment to provide longer term aftercare support for occupants for at least the first 12 months from occupation.
[edit] Applicable Schemes
The guidelines collated in this ISD aim to support sustainable best practice in the topic described. This issue may apply in multiple BREEAM schemes covering different stages in the life of a building, different building types and different year versions. Some content may be generic but scheme nuances should also be taken into account. Refer to the comments below and related articles to this one to understand these nuances. See this document for further guidelines.
- UK New Construction 2014
BRE Global does not endorse any of the content posted and use of the content will not guarantee the meeting of certification criteria.
--Multiple Author Article 16:25, 19 Apr 2018 (BST)
[edit] Related articles on Designing Buildings
Featured articles and news
What they are, how they work and why they are popular in many countries.
Plastic, recycling and its symbol
Student competition winning, M.C.Esher inspired Möbius strip design symbolising continuity within a finite entity.
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.
How neural technologies could transform the design future
Enhancing legacy parametric engines, offering novel ways to explore solutions and generate geometry.
Key AI related terms to be aware of
With explanations from the UK government and other bodies.
From QS to further education teacher
Applying real world skills with the next generation.
A guide on how children can use LEGO to mirror real engineering processes.
Data infrastructure for next-generation materials science
Research Data Express to automate data processing and create AI-ready datasets for materials research.
Wired for the Future with ECA; powering skills and progress
ECA South Wales Business Day 2025, a day to remember.
AI for the conservation professional
A level of sophistication previously reserved for science fiction.
Biomass harvested in cycles of less than ten years.
An interview with the new CIAT President
Usman Yaqub BSc (Hons) PCIAT MFPWS.
Cost benefit model report of building safety regime in Wales
Proposed policy option costs for design and construction stage of the new building safety regime in Wales.
Do you receive our free biweekly newsletter?
If not you can sign up to receive it in your mailbox here.